Oil Storage and Distribution
Project No 0316
Project Title Baku - Tblisi - Ceyhan (BTC) Crude Oil Pipeline Sivas - Ceyhan Section (Lot-C)
Client Punj Lloyd - Limak (PLL) Joint Venture
Start - Finish 2003 - 2005
Alone or Joint-Venture Alone
Detailed Description
Baku - Tbilisi - Ceyhan Crude Oil Pipeline
Sivas - Ceyhan Section (Lot C) 34, 42 inch, 330 km


River, Road and Railway Crossings
Irrigation Channels Crossings
Crossings at Steep Slopes and Side Slopes
Crossings at Land Slides
Concrete Coating of Pipes
Piping and Hydrostatic Tests
Construction and Installation Works at Ball Valve Stations
Mechanical Completion Reports for Ball Valve Stations
Hydrostatic Tests at Ball Valve Stations
Earth Works, Excavation and Backfilling
Concrete Works, Foundations, Structural Steel and Fencing
Permanent Access Roads
Electrical and Instrumentation Works
Route Changes
Field Engineering and Pre-Construction Survey
Cathodic Protection Systems
Work Method Statements and Procedures
As-Built Documentation
Services Provided By ESER
Construction Shop Drawings
Topographical Surveys
Construction Engineering Support Services