Oil Storage and Distribution
Project No 9917
Project Title Renewal of Pumps on Iskenderun - Malatya Pipeline
Client Ministry of Defense
Start - Finish 1999 - 2001
Alone or Joint-Venture Alone
Detailed Description
Renewal of Pump Groups at South Iskenderun, North Iskenderun, Narli, Golbasi and Malatya Pump Stations on 8 inch Iskenderun - Malatya Pipeline

14 each 200 cum /h, 360 mFS, High Pressure Pump
3 each 120 cum /h, 522 mFS, High Pressure Pump
17 each Gear Box
17 each Gas Tight Steel Wall
5 each Temperature Controlled Water Regulating Valve
13 each DN150 PN100 Ball Valve
14 each DN200 PN100 Ball Valve
HP Pump Stations Main Electrical Power and Distribution Switchgears
HP Pump Stations Electronic Control Systems
6 each 8 inch Emergency Connection Valve Pit Construction
1 each 6 inch Emergency Connection Valve Pit Construction
Services Provided By ESER
Detailed Engineering
Cost Estimations
Tender Evaluation
Tender Documentation
Construction Supervision
Construction Specifications
Operating and Maintenance Instructions
Commissioning
Start-up Inspections
Basic Engineering